ITAC Assessment: BD0129
ITAC logo
ITAC Assessment: BD0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Printed Paper and Packaging Materials
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area 76,000
ft2
Annual Production 6,700,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,072 3,164,420
kWh
Electricity Demand $69,101 7,470
kW-mo/yr
Electricity Fees $25,221 -
Natural Gas $6,901 1,363
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,094 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,561

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.2437: Recover waste heat from equipment $4,651 $2,500 $1,052
27,843
kWh
$239
-
kW-mo/yr
$3,360
-
MMBtu
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,778 $600 $2,778
72,978
kWh
$1,000
-
kW-mo/yr
- - - - -
03 2.3137: Use power during off-peak periods $3,669 - - $3,669
-
kW-mo/yr
- - - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,505 $2,200 $2,996
78,839
kWh
$999
-
kW-mo/yr
$(-1,490.0)
-
MMBtu
- - - -
05 2.7135: Install occupancy sensors $2,092 $1,350 $1,558
41,032
kWh
$534
-
kW-mo/yr
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $1,046 $600 $769
20,223
kWh
$277
-
kW-mo/yr
- - - - -
07 2.4133: Use most efficient type of electric motors $548 $560 $431
11,430
kWh
$117
-
kW-mo/yr
- - - - -
08 3.3122: Use filtration, centrifuging to remove contaminants $16,883 $16,000 $(-121.0)
(-3,224)
kWh
- - $17,784
-
gal
- $(-780.0) -
09 3.5315: Lease / purchase baler; sell cardboard to recycler $1,143 $250 - - - - $1,143
-
lb
- -
10 4.444: Install system to collect scrap $9,779 $5,000 $(-380.0)
(-9,965)
kWh
$(-241.0)
-
kW-mo/yr
- - - - $10,400
TOTAL RECOMMENDED $46,094 $29,060 $9,083
239,156
kWh
$6,594
-
kW-mo/yr
$1,870
-
MMBtu
$17,784
-
gal
$1,143
-
lb
$(-780.0) $10,400
TOTAL IMPLEMENTED $7,561 $2,760 $4,767
125,440
kWh
$1,651
-
kW-mo/yr
- - $1,143
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs