Assessment Year | 1999 |
---|---|
Principal Product | Printed Paper and Packaging Materials |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
76,000
ft2
|
Annual Production | 6,700,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $130,072 | 3,164,420 |
kWh
|
$0.041 |
Electricity Demand | $69,101 | 7,470 |
kW-mo/yr
|
$9.25 |
Electricity Fees | $25,221 | - |
|
- |
Natural Gas | $6,901 | 1,363 |
MMBtu
|
$5.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,094 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,561 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $4,651 | $2,500 |
$1,052
27,843
kWh
|
$239
-
kW-mo/yr
|
$3,360
-
MMBtu
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,778 | $600 |
$2,778
72,978
kWh
|
$1,000
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.3137: Use power during off-peak periods | $3,669 | - | - |
$3,669
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,505 | $2,200 |
$2,996
78,839
kWh
|
$999
-
kW-mo/yr
|
$(-1,490.0)
-
MMBtu
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $2,092 | $1,350 |
$1,558
41,032
kWh
|
$534
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,046 | $600 |
$769
20,223
kWh
|
$277
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $548 | $560 |
$431
11,430
kWh
|
$117
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 3.3122: Use filtration, centrifuging to remove contaminants | $16,883 | $16,000 |
$(-121.0)
(-3,224)
kWh
|
- | - |
$17,784
-
gal
|
- | $(-780.0) | - | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,143 | $250 | - | - | - | - |
$1,143
-
lb
|
- | - | |
10 | 4.444: Install system to collect scrap | $9,779 | $5,000 |
$(-380.0)
(-9,965)
kWh
|
$(-241.0)
-
kW-mo/yr
|
- | - | - | - | $10,400 | |
TOTAL RECOMMENDED | $46,094 | $29,060 |
$9,083
239,156
kWh
|
$6,594
-
kW-mo/yr
|
$1,870
-
MMBtu
|
$17,784
-
gal
|
$1,143
-
lb
|
$(-780.0) | $10,400 | ||
TOTAL IMPLEMENTED | $7,561 | $2,760 |
$4,767
125,440
kWh
|
$1,651
-
kW-mo/yr
|
- | - |
$1,143
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs