ITAC Assessment: CO0720
ITAC logo
ITAC Assessment: CO0720
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Plastic bottles
NAICS 326160: Plastics Bottle Manufacturing
SIC 3085: Plastics Bottles
Sales Range $10
M
to 50
M
# of Employees 29
Plant Area 148,232
ft2
Annual Production 90,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $627,007 15,828,155
kWh
Electricity Demand $663,885 35,579
kW-mo/yr
Electricity Fees $4,435 -
Natural Gas $15,380 2,110
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,110 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,030

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $14,640 $62,670 $6,630
180,000
kWh
$8,010
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,840 $300 $2,860
77,800
kWh
$1,980
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $14,190 $67,155 $11,980
325,100
kWh
$8,790
-
kW-mo/yr
$780 $(-7,360.0)
04 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $5,510 $27,600 $1,130
30,800
kWh
$4,380
-
kW-mo/yr
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $930 $1,330 $550
14,900
kWh
$380
-
kW-mo/yr
- -
TOTAL RECOMMENDED $40,110 $159,055 $23,150
628,600
kWh
$23,540
-
kW-mo/yr
$780 $(-7,360.0)
TOTAL IMPLEMENTED $19,030 $67,455 $14,840
402,900
kWh
$10,770
-
kW-mo/yr
$780 $(-7,360.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs