Assessment Year | 2016 |
---|---|
Principal Product | Electric motors and controllers |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $1 M to 5M |
# of Employees | 60 |
Plant Area |
126,988
ft2
|
Annual Production | 1,100
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $98,521 | 1,697,900 |
kWh
|
$0.058 |
Electricity Demand | $84,828 | 5,255 |
kW-mo/yr
|
$16.14 |
Electricity Fees | $1,584 | - |
|
- |
Natural Gas | $31,843 | 3,649 |
MMBtu
|
$8.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,280 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,840 | $3,490 |
$1,010
17,500
kWh
|
$830
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,060 | $50,310 |
$4,600
80,100
kWh
|
$6,200
-
kW-mo/yr
|
$170 | $(-1,910.0) | |
03 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $6,380 | $48,350 |
$1,960
34,100
kWh
|
$4,420
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $17,280 | $102,150 |
$7,570
131,700
kWh
|
$11,450
-
kW-mo/yr
|
$170 | $(-1,910.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs