ITAC Assessment: CO0717
ITAC logo
ITAC Assessment: CO0717
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Fire Trucks, Fans, Lighting Towers
NAICS 336120: Heavy Duty Truck Manufacturing
SIC 3711: Motor Vehicles and Passenger Car Bodies
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 160,000
ft2
Annual Production 3,000
pieces
Production Hrs. Annual 4,550
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,715 924,300
kWh
Electricity Demand $77,993 3,822
kW-mo/yr
Electricity Fees $570 -
Natural Gas $47,403 8,826
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1113: Reduce combustion air flow to optimum $1,160 $2,130 $340
8,700
kWh
- $820
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $470 $480 $190
5,000
kWh
$280
-
kW-mo/yr
- - - -
03 2.6218: Turn off equipment when not in use $380 $100 $380
9,800
kWh
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,880 $35,080 $2,130
55,100
kWh
$4,630
-
kW-mo/yr
- $90 - $1,030
05 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $3,660 $13,800 $720
18,500
kWh
$2,940
-
kW-mo/yr
- - - -
06 2.8121: Apply for tax-free status for energy purchases $3,270 $1,000 - - - - $3,270 -
07 2.2437: Recover waste heat from equipment $1,080 $3,220 - - $1,080
-
MMBtu
- - -
TOTAL RECOMMENDED $17,900 $55,810 $3,760
97,100
kWh
$7,850
-
kW-mo/yr
$1,900
-
MMBtu
$90 $3,270 $1,030
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs