| Assessment Year | 2015 |
|---|---|
| Principal Product | Lighting fixtures |
| NAICS | 335122: Commercial, Industrial, and Institutional Electric Lighting Fixture Manufacturing |
| SIC | 3646: Commercial, Industrial, and Institutional Electric Lighting Fixtures |
| Sales Range | $100 M to 500M |
| # of Employees | 400 |
| Plant Area |
191,000
ft2
|
| Annual Production | 200,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $90,243 | 2,034,900 |
kWh
|
$0.044 |
| Electricity Demand | $99,688 | 4,741 |
kW-mo/yr
|
$21.03 |
| Electricity Fees | $606 | - |
|
- |
| Natural Gas | $85,532 | 12,974 |
MMBtu
|
$6.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,940 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,900 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,900 | $1,270 |
$3,630
81,500
kWh
|
$3,270
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.6218: Turn off equipment when not in use | $4,710 | - |
$4,710
105,700
kWh
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,950 | $82,280 |
$8,230
184,700
kWh
|
$7,080
-
kW-mo/yr
|
- | $570 | $1,070 | |
| 04 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $4,840 | $15,500 |
$970
21,900
kWh
|
$3,870
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7243: Improve air circulation with destratification fans / other methods | $540 | $1,820 |
$(-340.0)
(-7,600)
kWh
|
$(-210.0)
-
kW-mo/yr
|
$1,090
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $33,940 | $100,870 |
$17,200
386,200
kWh
|
$14,010
-
kW-mo/yr
|
$1,090
-
MMBtu
|
$570 | $1,070 | ||
| TOTAL IMPLEMENTED | $6,900 | $1,270 |
$3,630
81,500
kWh
|
$3,270
-
kW-mo/yr
|
- | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs