ITAC Assessment: OK1083
ITAC logo
ITAC Assessment: OK1083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Aircraft assemblies
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 490
Plant Area 352,000
ft2
Annual Production 684
units
Production Hrs. Annual 5,880
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,169,955 21,271,900
kWh
Electricity Demand $344,113 54,795
kW-mo/yr
Natural Gas $173,530 53,230
MMBtu
Waste Disposal Costs
Water Usage $23,939 6,879
Tgal
Water Disposal $65,694 6,879
Tgal
TOTAL YEARLY COSTS $1,777,231
RECOMMENDED SAVINGS* $497,056 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $955

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2437: Recover waste heat from equipment $1,764 $522 - - $1,764
-
MMBtu
02 2.2414: Use waste heat from hot flue gases to preheat $3,133 $12,880 - - $3,133
-
MMBtu
03 2.2511: Insulate bare equipment $29 $123 $29
521
kWh
- -
04 2.9114: Use solar heat to make electricty $491,204 $4,927,139 $491,204
8,930,973
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $926 $2,799 $753
13,689
kWh
$173
-
kW-mo/yr
-
TOTAL RECOMMENDED $497,056 $4,943,463 $491,986
8,945,183
kWh
$173
-
kW-mo/yr
$4,897
-
MMBtu
TOTAL IMPLEMENTED $955 $2,922 $782
14,210
kWh
$173
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs