Assessment Year | 2014 |
---|---|
Principal Product | Precision optical components |
NAICS | 333314: Optical Instrument and Lens Manufacturing |
SIC | 3827: Optical Instruments and Lenses |
Sales Range | $5 M to 10M |
# of Employees | 33 |
Plant Area |
40,700
ft2
|
Annual Production | 22,000
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,886 | 1,342,080 |
kWh
|
$0.047 |
Electricity Demand | $58,530 | 2,641 |
kW-mo/yr
|
$22.16 |
Electricity Fees | $637 | - |
|
- |
Natural Gas | $13,494 | 1,792 |
MMBtu
|
$7.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,170 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $23,320 | $29,550 |
$(-1,500.0)
(-31,300)
kWh
|
$(-950.0)
-
kW-mo/yr
|
- | - | - | $25,770 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,760 | $1,550 |
$2,920
60,900
kWh
|
$1,840
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.9114: Use solar heat to make electricty | $13,090 | $87,610 |
$6,400
133,700
kWh
|
- | - | $6,690 | - | - | |
04 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $8,560 | $38,890 |
$3,760
78,400
kWh
|
$4,800
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $4,000 | $500 | - | - | - | $4,000 | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,440 | $5,180 |
$360
7,500
kWh
|
$900
-
kW-mo/yr
|
$20 | - | $160 | - | |
TOTAL RECOMMENDED | $55,170 | $163,280 |
$11,940
249,200
kWh
|
$6,590
-
kW-mo/yr
|
$20 | $10,690 | $160 | $25,770 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs