ITAC Assessment: CO0678
ITAC logo
ITAC Assessment: CO0678
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Lamb slaughtering and Processing
NAICS 311611: Animal (except Poultry) Slaughtering
SIC 2011: Meat Packing Plants
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 54,000
ft2
Annual Production 450,000
pieces
Production Hrs. Annual 2,990
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $152,485 3,824,132
kWh
Electricity Demand $175,780 8,536
kW-mo/yr
Electricity Fees $1,849 -
Natural Gas $123,711 21,865
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,920 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,780

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $6,330 $14,900 $2,410
57,400
kWh
$3,920
-
kW-mo/yr
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,540 $200 $1,320
31,500
kWh
$1,220
-
kW-mo/yr
- - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,340 $8,100 $1,380
32,900
kWh
$960
-
kW-mo/yr
- - - -
04 2.2136: Install / repair insulation on steam lines $890 $350 - - $890
-
MMBtu
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $13,580 $15,680 $7,020
167,600
kWh
$5,590
-
kW-mo/yr
- $190 - $780
06 2.8121: Apply for tax-free status for energy purchases $8,240 $1,500 - - - - $8,240 -
TOTAL RECOMMENDED $33,920 $40,730 $12,130
289,400
kWh
$11,690
-
kW-mo/yr
$890
-
MMBtu
$190 $8,240 $780
TOTAL IMPLEMENTED $10,780 $1,700 $1,320
31,500
kWh
$1,220
-
kW-mo/yr
- - $8,240 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs