| Assessment Year | 2012 |
|---|---|
| Principal Product | Prestressed concrete panels |
| NAICS | 327390: Other Concrete Product Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
10,000
ft2
|
| Annual Production | 45,600
pieces
|
| Production Hrs. Annual | 5,766
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $56,787 | 1,547,326 |
kWh
|
$0.037 |
| Electricity Demand | $84,222 | 4,766 |
kW-mo/yr
|
$17.67 |
| Electricity Fees | $4,461 | - |
|
- |
| Natural Gas | $197,378 | 39,059 |
MMBtu
|
$5.05 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,650 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,650 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2135: Repair and eliminate steam leaks | $8,050 | $1,440 | - | - |
$8,050
-
MMBtu
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,130 | $1,990 |
$1,310
39,100
kWh
|
$820
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $570 | $820 |
$210
6,200
kWh
|
$360
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,900 | $17,990 |
$3,080
92,300
kWh
|
$3,580
-
kW-mo/yr
|
- | $150 | $90 | |
| TOTAL RECOMMENDED | $17,650 | $22,240 |
$4,600
137,600
kWh
|
$4,760
-
kW-mo/yr
|
$8,050
-
MMBtu
|
$150 | $90 | ||
| TOTAL IMPLEMENTED | $17,650 | $22,240 |
$4,600
137,600
kWh
|
$4,760
-
kW-mo/yr
|
$8,050
-
MMBtu
|
$150 | $90 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs