ITAC Assessment: LT8396
ITAC logo
ITAC Assessment: LT8396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 167,700
ft2
Annual Production 42,000
thousand feet
Production Hrs. Annual 2,600
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $399,929 4,742,124
kWh
Electricity Demand $264,886 26,211
kW-mo/yr
Electricity Fees $63,893 -
Natural Gas $178,656 23,755
MMBtu
TOTAL YEARLY COSTS $907,364
RECOMMENDED SAVINGS* $10,892 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,001 $2,360 $663
7,862
kWh
$338
-
kW-mo/yr
-
02 2.3212: Optimize plant power factor $7,412 $31,808 - - $7,412
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,479 $1,067 $1,596
18,935
kWh
$883
-
kW-mo/yr
-
TOTAL RECOMMENDED $10,892 $35,235 $2,259
26,797
kWh
$1,222
-
kW-mo/yr
$7,412
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs