| Assessment Year | 2006 |
|---|---|
| Principal Product | Soft drinks |
| NAICS | 312111: Soft Drink Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
101,850
ft2
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 2,540
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $75,158 | 1,463,854 |
kWh
|
$0.051 |
| Electricity Demand | $51,728 | 8,815 |
kW-mo/yr
|
$5.87 |
| Electricity Fees | $1,787 | - |
|
- |
| Natural Gas | $64,497 | 6,950 |
MMBtu
|
$9.28 |
| Fuel Oil #2 | $180,000 | 9,694 |
MMBtu
|
$18.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,604 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,094 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $244 | $1,008 |
$111
2,756
kWh
|
$133
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,270 | $33,120 |
$16,650
246,600
kWh
|
- | - | - | $240 | $380 | |
| 03 | 2.8226: Increase efficiency of trucks | $5,740 | - | - | - | - |
$5,740
-
MMBtu
|
- | - | |
| 04 | 2.7442: Keep doors and windows shut when not on use | $3,810 | $1,000 | - | - |
$3,810
-
MMBtu
|
- | - | - | |
| 05 | 2.7131: Add area lighting switches | $2,410 | $100 |
$2,280
33,700
kWh
|
- | - | - | $60 | $70 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,120 | $9,260 |
$2,090
31,000
kWh
|
- | - | - | $10 | $20 | |
| 07 | 2.9114: Use solar heat to make electricty | $1,100 | $2,950 |
$1,100
15,200
kWh
|
- | - | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $910 | $5,740 |
$630
9,300
kWh
|
- | - | - | - | $280 | |
| TOTAL RECOMMENDED | $33,604 | $53,178 |
$22,861
338,556
kWh
|
$133
-
kW-mo/yr
|
$3,810
-
MMBtu
|
$5,740
-
MMBtu
|
$310 | $750 | ||
| TOTAL IMPLEMENTED | $30,094 | $50,128 |
$19,481
289,656
kWh
|
$133
-
kW-mo/yr
|
$3,810
-
MMBtu
|
$5,740
-
MMBtu
|
$250 | $680 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs