Assessment Year | 2006 |
---|---|
Principal Product | Aluminum beverage cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $10 M to 50M |
# of Employees | 72 |
Plant Area |
153,600
ft2
|
Annual Production | 759,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Wyoming |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $296,103 | 14,923,200 |
kWh
|
$0.020 |
Electricity Demand | $355,999 | 33,094 |
kW-mo/yr
|
$10.76 |
Electricity Fees | $101,408 | - |
|
- |
Natural Gas | $356,354 | 36,316 |
MMBtu
|
$9.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $68,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,388 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $18,970 | $780 |
$9,910
520,400
kWh
|
$9,060
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,390 | $290 |
$2,820
147,700
kWh
|
$2,570
-
kW-mo/yr
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $998 | $1,644 |
$522
27,387
kWh
|
$476
-
kW-mo/yr
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $3,950 | $630 | - | - |
$3,950
-
MMBtu
|
- | - | |
05 | 2.4131: Size electric motors for peak operating efficiency | $2,820 | $1,280 |
$1,470
77,100
kWh
|
$1,350
-
kW-mo/yr
|
- | - | - | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $13,170 | $40,400 | - | - |
$13,170
-
MMBtu
|
- | - | |
07 | 2.7243: Improve air circulation with destratification fans / other methods | $12,810 | $23,490 |
$(-360.0)
(-18,700)
kWh
|
$(-330.0)
-
kW-mo/yr
|
$13,500
-
MMBtu
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,630 | $15,320 |
$3,150
165,400
kWh
|
$1,930
-
kW-mo/yr
|
- | $300 | $250 | |
09 | 2.9111: Use solar heat to heat make-up air | $4,920 | $32,120 | - | - |
$4,920
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $68,658 | $115,954 |
$17,512
919,287
kWh
|
$15,056
-
kW-mo/yr
|
$35,540
-
MMBtu
|
$300 | $250 | ||
TOTAL IMPLEMENTED | $6,388 | $1,934 |
$3,342
175,087
kWh
|
$3,046
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs