ITAC Assessment: MA0800
ITAC logo
ITAC Assessment: MA0800
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Active Pharmaceutical Ingredients and Intermediates
NAICS 325412: Pharmaceutical Preparation Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 120,000
ft2
Annual Production 1,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $537,714 7,581,552
kWh
Electricity Demand $329,096 15,131
kW-mo/yr
Electricity Fees $4,185 -
Natural Gas $212,515 26,805
MMBtu
Waste Disposal Costs
Water Usage $10,023 1,027
Tgal
TOTAL YEARLY COSTS $1,093,533
RECOMMENDED SAVINGS* $15,069 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,661

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,227 $20,050 $5,227
73,619
kWh
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,117 $14,400 $4,117
57,994
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,064 $15,819 $1,845
25,985
kWh
$2,219
-
kW-mo/yr
04 2.4231: Reduce the pressure of compressed air to the minimum required $893 $500 $893
12,571
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $768 $500 $768
10,820
kWh
-
TOTAL RECOMMENDED $15,069 $51,269 $12,850
180,989
kWh
$2,219
-
kW-mo/yr
TOTAL IMPLEMENTED $1,661 $1,000 $1,661
23,391
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs