Assessment Year | 2019 |
---|---|
Principal Product | Active Pharmaceutical Ingredients and Intermediates |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
120,000
ft2
|
Annual Production | 1,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $537,714 | 7,581,552 |
kWh
|
$0.071 | |
Electricity Demand | $329,096 | 15,131 |
kW-mo/yr
|
$21.75 | |
Electricity Fees | $4,185 | - |
|
- | |
Natural Gas | $212,515 | 26,805 |
MMBtu
|
$7.93 | |
Waste Disposal Costs | |||||
Water Usage | $10,023 | 1,027 |
Tgal
|
$9.76 | |
TOTAL YEARLY COSTS | $1,093,533 | ||||
RECOMMENDED SAVINGS* | $15,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,661 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,227 | $20,050 |
$5,227
73,619
kWh
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,117 | $14,400 |
$4,117
57,994
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,064 | $15,819 |
$1,845
25,985
kWh
|
$2,219
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $893 | $500 |
$893
12,571
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $768 | $500 |
$768
10,820
kWh
|
- | |
TOTAL RECOMMENDED | $15,069 | $51,269 |
$12,850
180,989
kWh
|
$2,219
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $1,661 | $1,000 |
$1,661
23,391
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs