ITAC Assessment: CO0591
ITAC logo
ITAC Assessment: CO0591
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Electronic circuit boards, assemblies
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 109,835
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 5,590
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $118,073 2,942,400
kWh
Electricity Demand $21,709 7,956
kW-mo/yr
Electricity Fees $66,622 -
Natural Gas $22,243 1,927
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,540 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,350

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,430 $200 $1,540
38,000
kWh
$890
-
kW-mo/yr
- - -
02 2.6218: Turn off equipment when not in use $610 - $610
19,300
kWh
- - - -
03 2.4226: Use / purchase optimum sized compressor $260 $30 $160
4,000
kWh
$100
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,680 $5,290 $3,310
76,100
kWh
$2,120
-
kW-mo/yr
$70 - $180
05 2.9114: Use solar heat to make electricty $3,900 $32,600 $1,090
23,000
kWh
$870
-
kW-mo/yr
- $1,940 -
06 2.7135: Install occupancy sensors $1,350 $1,290 $800
18,500
kWh
$480
-
kW-mo/yr
$30 - $40
07 2.7122: Disconnect ballasts $310 $110 $170
3,900
kWh
$120
-
kW-mo/yr
$10 - $10
TOTAL RECOMMENDED $14,540 $39,520 $7,680
182,800
kWh
$4,580
-
kW-mo/yr
$110 $1,940 $230
TOTAL IMPLEMENTED $3,350 $310 $2,320
61,200
kWh
$1,010
-
kW-mo/yr
$10 - $10
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs