ITAC Assessment: CO0590
ITAC logo
ITAC Assessment: CO0590
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Paper cups and plates
NAICS 322219: Other Paperboard Container Manufacturing
SIC 2656: Sanitary Food Containers, Except Folding
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 170,000
ft2
Annual Production 1,300,000,000
pieces
Production Hrs. Annual 6,361
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $405,688 10,713,600
kWh
Electricity Demand $168,168 21,696
kW-mo/yr
Electricity Fees $64,749 -
Natural Gas $193,394 18,148
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,120 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,220

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1121: Use insulation in furnaces to facilitate heating / cooling $4,450 $770 - - $4,450
-
MMBtu
- - -
02 2.2136: Install / repair insulation on steam lines $2,900 $1,320 - - $2,900
-
MMBtu
- - -
03 2.4221: Install compressor air intakes in coolest locations $2,660 $100 $1,670
42,000
kWh
$990
-
kW-mo/yr
- - - -
04 2.4133: Use most efficient type of electric motors $560 $658 $360
9,361
kWh
$200
-
kW-mo/yr
- - - -
05 2.4239: Eliminate or reduce compressed air usage $1,880 - $1,230
32,200
kWh
$650
-
kW-mo/yr
- - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $670 $1,390 $440
11,600
kWh
$230
-
kW-mo/yr
- - - -
07 2.1134: Eliminate leaks in combustible gas lines $560 $500 - - $560
-
MMBtu
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $28,940 $70,090 $18,930
493,600
kWh
$8,890
-
kW-mo/yr
- $280 - $840
09 2.9114: Use solar heat to make electricty $3,850 $32,600 $1,060
23,000
kWh
$850
-
kW-mo/yr
- - $1,940 -
10 2.7135: Install occupancy sensors $1,280 $680 $680
16,300
kWh
$530
-
kW-mo/yr
- $20 - $50
11 2.7135: Install occupancy sensors $210 $780 $180
5,000
kWh
$30
-
kW-mo/yr
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $160 $500 $40
1,000
kWh
$10
-
kW-mo/yr
- $50 - $60
TOTAL RECOMMENDED $48,120 $109,388 $24,590
634,061
kWh
$12,380
-
kW-mo/yr
$7,910
-
MMBtu
$350 $1,940 $950
TOTAL IMPLEMENTED $5,220 $2,438 $2,750
68,661
kWh
$1,730
-
kW-mo/yr
$560
-
MMBtu
$70 - $110
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs