ITAC Assessment: CO0553
ITAC logo
ITAC Assessment: CO0553
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Custom industrial pumps, shafts
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $100
M
to 500
M
# of Employees 40
Plant Area 45,800
ft2
Annual Production 420
pieces
Production Hrs. Annual 4,992
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,501 1,385,004
kWh
Electricity Demand $6,168 4,458
kW-mo/yr
Electricity Fees $29,777 -
Natural Gas $16,056 2,166
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,600 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,980

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4224: Upgrade controls on compressors $5,190 $20,000 $4,250
58,100
kWh
$940
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,980 $180 $2,650
36,100
kWh
$330
-
kW-mo/yr
- -
03 2.2437: Recover waste heat from equipment $2,260 $3,020 - - $2,260
-
MMBtu
-
04 2.4222: Install adequate dryers on air lines to eliminate blowdown $2,260 $8,700 $1,730
23,600
kWh
$530
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $8,930 $20,520 $8,850
120,800
kWh
$1,110
-
kW-mo/yr
- $(-1,030.0)
06 2.7243: Improve air circulation with destratification fans / other methods $4,620 $15,230 $(-680.0)
(-11,600)
kWh
$(-60.0)
-
kW-mo/yr
$5,360
-
MMBtu
-
07 2.7135: Install occupancy sensors $360 $520 $300
3,300
kWh
- $60
-
MMBtu
-
TOTAL RECOMMENDED $26,600 $68,170 $17,100
230,300
kWh
$2,850
-
kW-mo/yr
$7,680
-
MMBtu
$(-1,030.0)
TOTAL IMPLEMENTED $2,980 $180 $2,650
36,100
kWh
$330
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs