Assessment Year | 2004 |
---|---|
Principal Product | Wireless communication components |
NAICS | 334419: Other Electronic Component Manufacturing |
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 150 |
Plant Area |
250,000
ft2
|
Annual Production | 225,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | New Mexico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $747,506 | 19,324,800 |
kWh
|
$0.039 |
Electricity Demand | $281,154 | 30,888 |
kW-mo/yr
|
$9.10 |
Electricity Fees | $69,787 | - |
|
- |
Natural Gas | $159,712 | 27,345 |
MMBtu
|
$5.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,754 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,904 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $47,960 | $7,780 |
$34,220
902,200
kWh
|
$13,740
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,570 | $620 |
$5,400
142,400
kWh
|
$2,170
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,520 | $270 |
$3,940
103,900
kWh
|
$1,580
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $834 | $560 |
$595
15,709
kWh
|
$239
-
kW-mo/yr
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,500 | $3,050 |
$1,070
28,100
kWh
|
$430
-
kW-mo/yr
|
- | - | - | |
06 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $14,250 | $71,200 |
$10,500
286,900
kWh
|
$3,750
-
kW-mo/yr
|
- | - | - | |
07 | 3.4115: Recover and reuse cooling water | $4,170 | $20,000 | - |
$(-820.0)
-
kW-mo/yr
|
$1,990
-
Tgal
|
$(-480.0) |
$3,480
-
Tgal
|
|
08 | 2.7135: Install occupancy sensors | $950 | $2,800 |
$860
22,800
kWh
|
$90
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $82,754 | $106,280 |
$56,585
1,502,009
kWh
|
$21,179
-
kW-mo/yr
|
$1,990
-
Tgal
|
$(-480.0) |
$3,480
-
Tgal
|
||
TOTAL IMPLEMENTED | $9,904 | $4,230 |
$7,065
186,209
kWh
|
$2,839
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs