Assessment Year | 2004 |
---|---|
Principal Product | Passenger railcars |
NAICS | 336510: Railroad Rolling Stock Manufacturing |
SIC | 3743: Railroad Equipment |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
87,040
ft2
|
Annual Production | 6
pieces
|
Production Hrs. Annual | 2,700
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,990 | 667,520 |
kWh
|
$0.037 |
Electricity Demand | $40,295 | 2,918 |
kW-mo/yr
|
$13.81 |
Electricity Fees | $1,008 | - |
|
- |
Natural Gas | $33,653 | 4,621 |
MMBtu
|
$7.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,200 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,580 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,960 | $2,000 | - | - |
$1,960
-
MMBtu
|
- | - | - | - | |
02 | 3.8142: Distill contaminated solvents for reuse | $1,720 | $6,070 | - |
$(-70.0)
-
kW-mo/yr
|
- |
$1,600
-
gal
|
$(-500.0) | - | $690 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,000 | $180 |
$330
8,900
kWh
|
$670
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $590 | $3,520 |
$110
3,000
kWh
|
$480
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $490 | - |
$190
5,100
kWh
|
$300
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $6,160 | $23,870 |
$(-710.0)
(-19,000)
kWh
|
$(-360.0)
-
kW-mo/yr
|
$7,230
-
MMBtu
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,040 | $77,000 |
$1,490
39,700
kWh
|
$2,430
-
kW-mo/yr
|
- | - | $80 | - | $40 | |
08 | 2.8121: Apply for tax-free status for energy purchases | $2,570 | $1,000 | - | - | - | - | - | $2,570 | - | |
09 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,210 | $17,000 | - | - |
$2,210
-
MMBtu
|
- | - | - | - | |
10 | 2.7131: Add area lighting switches | $2,070 | $4,850 |
$690
18,400
kWh
|
$1,260
-
kW-mo/yr
|
- | - | $60 | - | $60 | |
11 | 4.821: Pay bills on time to avoid late fees | $390 | - | - | - | - | - | - | $390 | - | |
TOTAL RECOMMENDED | $23,200 | $135,490 |
$2,100
56,100
kWh
|
$4,710
-
kW-mo/yr
|
$11,400
-
MMBtu
|
$1,600
-
gal
|
$(-360.0) | $2,960 | $790 | ||
TOTAL IMPLEMENTED | $8,580 | $11,550 |
$1,130
30,300
kWh
|
$2,410
-
kW-mo/yr
|
$1,960
-
MMBtu
|
- | $60 | $2,960 | $60 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs