ITAC Assessment: CO0534
ITAC logo
ITAC Assessment: CO0534
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Thin-film coating machines
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 60,000
ft2
Annual Production 6
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,379 4,001,333
kWh
Electricity Demand $114,937 9,196
kW-mo/yr
Electricity Fees $180 -
Natural Gas $3,605 900
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,721 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,800

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,330 $19,000 n/a $5,670
188,400
kWh
$4,540
-
kW-mo/yr
$80 $(-960.0)
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,800 $930 $4,330
143,800
kWh
$2,470
-
kW-mo/yr
- -
03 2.4226: Use / purchase optimum sized compressor $2,520 $2,300 $2,520
83,600
kWh
- - -
04 2.7135: Install occupancy sensors $1,690 $6,230 $840
27,800
kWh
$680
-
kW-mo/yr
$80 $90
05 2.7135: Install occupancy sensors $1,520 $1,070 $760
24,900
kWh
$650
-
kW-mo/yr
$30 $80
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,171 $656 $823
27,331
kWh
$657
-
kW-mo/yr
- $(-309.0)
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $980 $2,750 $610
20,100
kWh
$370
-
kW-mo/yr
- -
08 2.4221: Install compressor air intakes in coolest locations $710 $620 $450
15,000
kWh
$260
-
kW-mo/yr
- -
TOTAL RECOMMENDED $24,721 $33,556 $16,003
530,931
kWh
$9,627
-
kW-mo/yr
$190 $(-1,099.0)
TOTAL IMPLEMENTED $6,800 $930 $4,330
143,800
kWh
$2,470
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs