ITAC Assessment: CO0519
ITAC logo
ITAC Assessment: CO0519
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product frozen green chile peppers, tortillas
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 120,500
ft2
Annual Production 8,000,000
lb
Production Hrs. Annual 6,552
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $253,401 6,307,200
kWh
Electricity Demand $69,241 11,979
kW-mo/yr
Electricity Fees $70,732 -
Natural Gas $111,922 26,748
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,035 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,315

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.2511: Insulate bare equipment $5,560 $1,350 - - $5,560
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,972 $5,292 $1,860
46,850
kWh
$776
-
kW-mo/yr
- $336
03 2.7142: Utilize higher efficiency lamps and/or ballasts $954 $3,156 $682
16,596
kWh
$318
-
kW-mo/yr
- $(-46.0)
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,390 $2,700 $1,300
31,200
kWh
$660
-
kW-mo/yr
$(-570.0)
-
MMBtu
-
05 2.4225: Install common header on compressors $770 $2,740 $550
13,900
kWh
$220
-
kW-mo/yr
- -
06 2.4133: Use most efficient type of electric motors $103 $280 $72
1,817
kWh
$31
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $286 $742 $294
6,988
kWh
$160
-
kW-mo/yr
- $(-168.0)
TOTAL RECOMMENDED $12,035 $16,260 $4,758
117,351
kWh
$2,165
-
kW-mo/yr
$4,990
-
MMBtu
$122
TOTAL IMPLEMENTED $4,315 $9,470 $2,908
72,251
kWh
$1,285
-
kW-mo/yr
- $122
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs