| Assessment Year | 2002 |
|---|---|
| Principal Product | frozen green chile peppers, tortillas |
| NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
120,500
ft2
|
| Annual Production | 8,000,000
lb
|
| Production Hrs. Annual | 6,552
hrs
|
| Location (State) | New Mexico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $253,401 | 6,307,200 |
kWh
|
$0.040 |
| Electricity Demand | $69,241 | 11,979 |
kW-mo/yr
|
$5.78 |
| Electricity Fees | $70,732 | - |
|
- |
| Natural Gas | $111,922 | 26,748 |
MMBtu
|
$4.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,315 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $5,560 | $1,350 | - | - |
$5,560
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,972 | $5,292 |
$1,860
46,850
kWh
|
$776
-
kW-mo/yr
|
- | $336 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $954 | $3,156 |
$682
16,596
kWh
|
$318
-
kW-mo/yr
|
- | $(-46.0) | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,390 | $2,700 |
$1,300
31,200
kWh
|
$660
-
kW-mo/yr
|
$(-570.0)
-
MMBtu
|
- | |
| 05 | 2.4225: Install common header on compressors | $770 | $2,740 |
$550
13,900
kWh
|
$220
-
kW-mo/yr
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $103 | $280 |
$72
1,817
kWh
|
$31
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $286 | $742 |
$294
6,988
kWh
|
$160
-
kW-mo/yr
|
- | $(-168.0) | |
| TOTAL RECOMMENDED | $12,035 | $16,260 |
$4,758
117,351
kWh
|
$2,165
-
kW-mo/yr
|
$4,990
-
MMBtu
|
$122 | ||
| TOTAL IMPLEMENTED | $4,315 | $9,470 |
$2,908
72,251
kWh
|
$1,285
-
kW-mo/yr
|
- | $122 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs