| Assessment Year | 2001 |
|---|---|
| Principal Product | Injection molded plastics parts |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 56 |
| Plant Area |
44,450
ft2
|
| Annual Production | 13,900,000
pieces
|
| Production Hrs. Annual | 6,656
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $93,176 | 2,969,880 |
kWh
|
$0.031 |
| Electricity Demand | $68,242 | 7,063 |
kW-mo/yr
|
$9.66 |
| Electricity Fees | $132 | - |
|
- |
| Natural Gas | $3,296 | 291 |
MMBtu
|
$11.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $136,660 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,820 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,240 | $84,240 |
$16,870
537,900
kWh
|
$9,370
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.3191: Use demand controller or load shedder | $3,480 | $7,000 | - |
$3,480
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $610 | $260 |
$620
19,900
kWh
|
$350
-
kW-mo/yr
|
- | $(-360.0) | - | - | |
| 04 | 2.7442: Keep doors and windows shut when not on use | $540 | $900 | - | - |
$540
-
MMBtu
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $190 | - |
$970
30,900
kWh
|
$590
-
kW-mo/yr
|
- | $(-460.0) | - | $(-910.0) | |
| 06 | 4.211: Consider use / purchase of bulk materials where possible | $105,600 | $120,000 | - | - | - | - | $45,600 | $60,000 | |
| TOTAL RECOMMENDED | $136,660 | $212,400 |
$18,460
588,700
kWh
|
$13,790
-
kW-mo/yr
|
$540
-
MMBtu
|
$(-820.0) | $45,600 | $59,090 | ||
| TOTAL IMPLEMENTED | $4,820 | $8,160 |
$1,590
50,800
kWh
|
$4,420
-
kW-mo/yr
|
$540
-
MMBtu
|
$(-820.0) | - | $(-910.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs