Assessment Year | 2001 |
---|---|
Principal Product | Natural gas compressors and wheelchair lifts |
NAICS |
n/a
|
SIC | 3563: Air and Gas Compressors |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
56,600
ft2
|
Annual Production | 35
pieces
|
Production Hrs. Annual | 2,496
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $13,321 | 798,400 |
kWh
|
$0.017 |
Electricity Demand | $38,803 | 2,868 |
kW-mo/yr
|
$13.53 |
Electricity Fees | $196 | - |
|
- |
Natural Gas | $51,920 | 7,072 |
MMBtu
|
$7.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $75,200 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $3,880 | $7,000 | - |
$3,880
-
kW-mo/yr
|
- | - | - | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $2,910 | $5,800 | - | - |
$2,910
-
MMBtu
|
- | - | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,110 | $7,530 | - | - |
$2,110
-
MMBtu
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $410 | - |
$1,040
62,100
kWh
|
$3,770
-
kW-mo/yr
|
- | $(-1,370.0) | $(-3,030.0) | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $380 | $210 |
$280
16,600
kWh
|
$700
-
kW-mo/yr
|
- | $(-600.0) | - | |
06 | 4.513: Re-arrange equipment layout to reduce labor costs | $71,500 | $3,200 | - | - | - | $71,500 | - | |
TOTAL RECOMMENDED | $81,190 | $23,740 |
$1,320
78,700
kWh
|
$8,350
-
kW-mo/yr
|
$5,020
-
MMBtu
|
$69,530 | $(-3,030.0) | ||
TOTAL IMPLEMENTED | $75,200 | $9,210 |
$1,320
78,700
kWh
|
$4,470
-
kW-mo/yr
|
$2,910
-
MMBtu
|
$69,530 | $(-3,030.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs