| Assessment Year | 2001 |
|---|---|
| Principal Product | Natural gas compressors and wheelchair lifts |
| NAICS |
n/a
|
| SIC | 3563: Air and Gas Compressors |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
56,600
ft2
|
| Annual Production | 35
pieces
|
| Production Hrs. Annual | 2,496
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $13,321 | 798,400 |
kWh
|
$0.017 |
| Electricity Demand | $38,803 | 2,868 |
kW-mo/yr
|
$13.53 |
| Electricity Fees | $196 | - |
|
- |
| Natural Gas | $51,920 | 7,072 |
MMBtu
|
$7.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $81,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $75,200 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $3,880 | $7,000 | - |
$3,880
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7221: Lower temperature during the winter season and vice-versa | $2,910 | $5,800 | - | - |
$2,910
-
MMBtu
|
- | - | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,110 | $7,530 | - | - |
$2,110
-
MMBtu
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $410 | - |
$1,040
62,100
kWh
|
$3,770
-
kW-mo/yr
|
- | $(-1,370.0) | $(-3,030.0) | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $380 | $210 |
$280
16,600
kWh
|
$700
-
kW-mo/yr
|
- | $(-600.0) | - | |
| 06 | 4.513: Re-arrange equipment layout to reduce labor costs | $71,500 | $3,200 | - | - | - | $71,500 | - | |
| TOTAL RECOMMENDED | $81,190 | $23,740 |
$1,320
78,700
kWh
|
$8,350
-
kW-mo/yr
|
$5,020
-
MMBtu
|
$69,530 | $(-3,030.0) | ||
| TOTAL IMPLEMENTED | $75,200 | $9,210 |
$1,320
78,700
kWh
|
$4,470
-
kW-mo/yr
|
$2,910
-
MMBtu
|
$69,530 | $(-3,030.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs