Assessment Year | 2001 |
---|---|
Principal Product | contract manufacturer of medical, communications and misc. e |
NAICS |
n/a
|
SIC | 3826: Laboratory Analytical Instruments |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
64,350
ft2
|
Annual Production | 120,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $21,293 | 699,100 |
kWh
|
$0.030 |
Electricity Demand | $17,982 | 1,917 |
kW-mo/yr
|
$9.38 |
Electricity Fees | $120 | - |
|
- |
Natural Gas | $7,077 | 1,537 |
MMBtu
|
$4.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,780 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $1,690 | $2,000 | - |
$1,690
-
kW-mo/yr
|
- | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $1,370 | - |
$1,370
45,000
kWh
|
- | - | - | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $1,230 | $880 | - | - |
$1,230
-
MMBtu
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $1,030 | - |
$1,030
33,800
kWh
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $870 | $130 |
$670
22,100
kWh
|
$560
-
kW-mo/yr
|
- | - | $(-360.0) | |
06 | 2.2211: Use optimum temperature | $820 | $2,330 | - | - |
$820
-
MMBtu
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $480 | $30 |
$260
8,400
kWh
|
$220
-
kW-mo/yr
|
- | - | - | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $300 | $130 | - | - |
$300
-
MMBtu
|
- | - | |
09 | 3.5316: Contract a wood pallet recycling company | $160 | - | - | - | - |
$160
-
lb
|
- | |
TOTAL RECOMMENDED | $7,950 | $5,500 |
$3,330
109,300
kWh
|
$2,470
-
kW-mo/yr
|
$2,350
-
MMBtu
|
$160
-
lb
|
$(-360.0) | ||
TOTAL IMPLEMENTED | $5,780 | $3,470 |
$3,070
100,900
kWh
|
$560
-
kW-mo/yr
|
$2,350
-
MMBtu
|
$160
-
lb
|
$(-360.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs