Assessment Year | 1999 |
---|---|
Principal Product | corrugated containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
121,000
ft2
|
Annual Production | 120,000,000
thousand feet
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,501 | 694,021 |
kWh
|
$0.021 |
Electricity Demand | $47,672 | 3,460 |
kW-mo/yr
|
$13.78 |
Electricity Fees | $516 | - |
|
- |
Natural Gas | $10,288 | 2,256 |
MMBtu
|
$4.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $203,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,820 | $4,000 | n/a | - |
$4,820
-
kW-mo/yr
|
- | - | - | - |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $830 | $1,080 | n/a | - | - |
$830
-
MMBtu
|
- | - | - |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $430 | $30 | n/a |
$430
6,155
kWh
|
- | - | - | - | - |
04 | 2.7224: Reduce space conditioning during non-working hours | $380 | $150 | n/a |
$80
4,103
kWh
|
- |
$300
-
MMBtu
|
- | - | - |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $330 | $210 | n/a |
$1,110
42,790
kWh
|
- | - | $(-780.0) | - | - |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20 | - | n/a |
$100
5,569
kWh
|
$200
-
kW-mo/yr
|
- | $(-40.0) | $(-240.0) | - |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $160,300 | $489,000 | n/a | - | - | - | - | - | $160,300 |
08 | 4.625: Develop standard operating procedures | $36,000 | - | n/a | - | - | - | - | - | $36,000 |
TOTAL RECOMMENDED | $203,110 | $494,470 |
$1,720
58,617
kWh
|
$5,020
-
kW-mo/yr
|
$1,130
-
MMBtu
|
$(-820.0) | $(-240.0) | $196,300 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs