| Assessment Year | 1999 |
|---|---|
| Principal Product | concrete landscape products |
| NAICS |
n/a
|
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
20,000
ft2
|
| Annual Production | 110,000
ton
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $39,382 | 1,043,963 |
kWh
|
$0.038 |
| Electricity Demand | $27,834 | 3,510 |
kW-mo/yr
|
$7.93 |
| Electricity Fees | $1,014 | - |
|
- |
| Natural Gas | $20,779 | 5,085 |
MMBtu
|
$4.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $55,971 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $36,701 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $141 | $566 |
$226
7,913
kWh
|
$115
-
kW-mo/yr
|
- | - | - | - | - | $(-200.0) | - | - | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $180 | $800 | - | - |
$180
-
MMBtu
|
- | - | - | - | - | - | - | |
| 03 | 3.6192: Use a less expensive method of waste removal | $5,460 | - | - | - | - | - |
$5,460
-
lb
|
- | - | - | - | - | |
| 04 | 4.625: Develop standard operating procedures | $31,100 | - | - | - | - | - | - | $23,900 | $4,200 | - | - | $3,000 | |
| 05 | 4.631: Install an uninteruptable power supply | $19,090 | $75,000 | - | - | - |
$(-12,010.0)
-
MMBtu
|
- | $23,900 | $4,200 | - | $3,000 | - | |
| TOTAL RECOMMENDED | $55,971 | $76,366 |
$226
7,913
kWh
|
$115
-
kW-mo/yr
|
$180
-
MMBtu
|
$(-12,010.0)
-
MMBtu
|
$5,460
-
lb
|
$47,800 | $8,400 | $(-200.0) | $3,000 | $3,000 | ||
| TOTAL IMPLEMENTED | $36,701 | $566 |
$226
7,913
kWh
|
$115
-
kW-mo/yr
|
- | - |
$5,460
-
lb
|
$23,900 | $4,200 | $(-200.0) | - | $3,000 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs