| Assessment Year | 1999 |
|---|---|
| Principal Product | thermoformed plastic components |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 11 |
| Plant Area |
19,000
ft2
|
| Annual Production | 8,790,000
pieces
|
| Production Hrs. Annual | 2,184
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $9,542 | 538,394 |
kWh
|
$0.018 |
| Electricity Demand | $44,585 | 3,270 |
kW-mo/yr
|
$13.63 |
| Electricity Fees | $204 | - |
|
- |
| Natural Gas | $5,757 | 1,049 |
MMBtu
|
$5.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $77,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,630 | $1,400 | - |
$1,630
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $1,250 | $600 | - | - |
$1,250
-
MMBtu
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $441 | $1,208 |
$98
5,569
kWh
|
$343
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $960 | - |
$960
53,927
kWh
|
- | - | - | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $460 | $420 |
$90
4,982
kWh
|
$370
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 3.6192: Use a less expensive method of waste removal | $340 | - | - | - | - |
$340
-
lb
|
- | - | |
| 07 | 3.6192: Use a less expensive method of waste removal | $220 | $20 | - | - | - | - |
$220
-
lb
|
- | |
| 08 | 4.111: Add equipment/ operators to reduce production bottleneck | $71,760 | $60,000 | - | - | - | - | - | $71,760 | |
| TOTAL RECOMMENDED | $77,061 | $63,648 |
$1,148
64,478
kWh
|
$2,343
-
kW-mo/yr
|
$1,250
-
MMBtu
|
$340
-
lb
|
$220
-
lb
|
$71,760 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs