Assessment Year | 1999 |
---|---|
Principal Product | flavor extracts & herbal products |
NAICS |
n/a
|
SIC | 2833: Medicinal Chemicals and Botanical Products |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
28,500
ft2
|
Annual Production | 24,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $81,762 | 2,370,164 |
kWh
|
$0.034 |
Electricity Demand | $33,663 | 4,119 |
kW-mo/yr
|
$8.17 |
Electricity Fees | $1,054 | - |
|
- |
Natural Gas | $83,297 | 16,152 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $707,050 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $702,330 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $16,420 | $21,500 |
$10,750
351,700
kWh
|
$5,670
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.1222: Install turbulators | $1,830 | $3,630 | - | - |
$1,830
-
MMBtu
|
- | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,340 | $610 |
$880
28,722
kWh
|
$460
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 3.1182: Make a new by-product | $4,350 | $19,100 | - | - | - |
$5,400
-
lb
|
$(-1,050.0) | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $370 | - | - | - | - |
$370
-
lb
|
- | - | - | - | |
06 | 4.114: Add/modify equipment to improve drying process | $638,100 | - | - | - | - | - | - | $60,600 | - | $577,500 | |
07 | 4.431: Train operators for maximum operating efficiency | $44,640 | - | - | - | - | - | $(-86,400.0) | - | $131,040 | - | |
TOTAL RECOMMENDED | $707,050 | $44,840 |
$11,630
380,422
kWh
|
$6,130
-
kW-mo/yr
|
$1,830
-
MMBtu
|
$5,770
-
lb
|
$(-87,450.0) | $60,600 | $131,040 | $577,500 | ||
TOTAL IMPLEMENTED | $702,330 | $25,740 |
$11,630
380,422
kWh
|
$6,130
-
kW-mo/yr
|
$1,830
-
MMBtu
|
- | $(-86,400.0) | $60,600 | $131,040 | $577,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs