| Assessment Year | 1998 |
|---|---|
| Principal Product | bricks |
| NAICS |
n/a
|
| SIC | 3251: Brick and Structural Clay Tile |
| Sales Range | $1 M to 5M |
| # of Employees | 35 |
| Plant Area |
55,000
ft2
|
| Annual Production | 15,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $25,493 | 1,438,453 |
kWh
|
$0.018 |
| Electricity Demand | $74,207 | 10,225 |
kW-mo/yr
|
$7.26 |
| Electricity Fees | $1,666 | - |
|
- |
| Natural Gas | $235,263 | 90,908 |
MMBtu
|
$2.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $60,270 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,280 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $500 | $2,082 |
$197
11,137
kWh
|
$303
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $290 | $1,000 |
$90
5,275
kWh
|
$200
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $240 | $40 |
$70
4,103
kWh
|
$170
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $210 | - | - | - |
$210
-
lb
|
- | - | |
| 05 | 4.621: Use fixtures to reduce machine changeout times | $34,700 | $300,000 | - | - | - | - | $34,700 | |
| 06 | 4.621: Use fixtures to reduce machine changeout times | $6,080 | $30,000 | - | - | - | - | $6,080 | |
| 07 | 4.653: Maintain/enlarge a stock of spare parts | $18,250 | $27,000 | - | - | - | $18,250 | - | |
| TOTAL RECOMMENDED | $60,270 | $360,122 |
$357
20,515
kWh
|
$673
-
kW-mo/yr
|
$210
-
lb
|
$18,250 | $40,780 | ||
| TOTAL IMPLEMENTED | $19,280 | $30,122 |
$357
20,515
kWh
|
$673
-
kW-mo/yr
|
- | $18,250 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs