Assessment Year | 1998 |
---|---|
Principal Product | printed circuit boards & assembled electronic components |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
42,600
ft2
|
Annual Production | 63,650
thousand feet
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | New Mexico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $133,255 | 1,474,502 |
kWh
|
$0.090 |
Electricity Demand | $15,107 | 3,572 |
kW-mo/yr
|
$4.23 |
Electricity Fees | $2,821 | - |
|
- |
Natural Gas | $9,967 | 2,352 |
MMBtu
|
$4.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $333,625 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $270,435 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,680 | $1,230 | - | - |
$1,680
-
MMBtu
|
- | - | - | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $155 | $227 |
$134
2,052
kWh
|
$21
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $860 | $50 |
$730
10,844
kWh
|
$130
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.6218: Turn off equipment when not in use | $390 | - |
$390
4,689
kWh
|
- | - | - | - | - | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $350 | $420 |
$300
4,396
kWh
|
$50
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,560 | - | - | - | - |
$1,560
-
lb
|
- | - | - | - | - | |
07 | 3.6192: Use a less expensive method of waste removal | $630 | - | - | - | - | - |
$630
-
lb
|
- | - | - | - | |
08 | 4.431: Train operators for maximum operating efficiency | $148,000 | $560 | - | - | - | - | - | - | - | - | $148,000 | |
09 | 4.512: Condense operation into one building | $119,000 | $55,330 | - | - | - | - | - | $200,000 | $(-81,000.0) | - | - | |
10 | 4.122: Develop standard procedures to improve internal yields | $61,000 | - | - | - | - | - | - | $5,000 | - | $56,000 | - | |
TOTAL RECOMMENDED | $333,625 | $57,817 |
$1,554
21,981
kWh
|
$201
-
kW-mo/yr
|
$1,680
-
MMBtu
|
$1,560
-
lb
|
$630
-
lb
|
$205,000 | $(-81,000.0) | $56,000 | $148,000 | ||
TOTAL IMPLEMENTED | $270,435 | $57,817 |
$1,554
21,981
kWh
|
$201
-
kW-mo/yr
|
$1,680
-
MMBtu
|
- | - | $200,000 | $(-81,000.0) | - | $148,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs