ITAC Assessment: CO0417
ITAC logo
ITAC Assessment: CO0417
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product printed circuit boards & assembled electronic components
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 42,600
ft2
Annual Production 63,650
thousand feet
Production Hrs. Annual 4,420
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,255 1,474,502
kWh
Electricity Demand $15,107 3,572
kW-mo/yr
Electricity Fees $2,821 -
Natural Gas $9,967 2,352
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $333,625 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $270,435

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
01 2.2437: Recover waste heat from equipment $1,680 $1,230 - - $1,680
-
MMBtu
- - - - - -
02 2.4133: Use most efficient type of electric motors $155 $227 $134
2,052
kWh
$21
-
kW-mo/yr
- - - - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $860 $50 $730
10,844
kWh
$130
-
kW-mo/yr
- - - - - - -
04 2.6218: Turn off equipment when not in use $390 - $390
4,689
kWh
- - - - - - - -
05 2.4221: Install compressor air intakes in coolest locations $350 $420 $300
4,396
kWh
$50
-
kW-mo/yr
- - - - - - -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $1,560 - - - - $1,560
-
lb
- - - - -
07 3.6192: Use a less expensive method of waste removal $630 - - - - - $630
-
lb
- - - -
08 4.431: Train operators for maximum operating efficiency $148,000 $560 - - - - - - - - $148,000
09 4.512: Condense operation into one building $119,000 $55,330 - - - - - $200,000 $(-81,000.0) - -
10 4.122: Develop standard procedures to improve internal yields $61,000 - - - - - - $5,000 - $56,000 -
TOTAL RECOMMENDED $333,625 $57,817 $1,554
21,981
kWh
$201
-
kW-mo/yr
$1,680
-
MMBtu
$1,560
-
lb
$630
-
lb
$205,000 $(-81,000.0) $56,000 $148,000
TOTAL IMPLEMENTED $270,435 $57,817 $1,554
21,981
kWh
$201
-
kW-mo/yr
$1,680
-
MMBtu
- - $200,000 $(-81,000.0) - $148,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs