ITAC Assessment: CO0412
ITAC logo
ITAC Assessment: CO0412
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product wireless communications equipt.
NAICS
n/a
SIC 3661: Telephone and Telegraph Apparatus
Sales Range $5
M
to 10
M
# of Employees 250
Plant Area 76,000
ft2
Annual Production 100
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $178,667 4,729,191
kWh
Electricity Demand $50,744 11,126
kW-mo/yr
Electricity Fees $4,872 -
Natural Gas $11,087 2,796
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,121 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,333

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,288 $6,148 $543
27,550
kWh
$745
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,694 $9,850 $1,694
31,067
kWh
- -
03 2.7122: Disconnect ballasts $5,060 $3,330 $2,080
71,219
kWh
$2,980
-
kW-mo/yr
-
04 2.7122: Disconnect ballasts $1,230 $900 $1,230
22,567
kWh
- -
05 2.4133: Use most efficient type of electric motors $149 $114 $149
2,638
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $220 $300 $90
2,931
kWh
$130
-
kW-mo/yr
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $220 $670 $160
5,862
kWh
$60
-
kW-mo/yr
-
08 3.6192: Use a less expensive method of waste removal $1,260 - - - $1,260
-
lb
TOTAL RECOMMENDED $11,121 $21,312 $5,946
163,834
kWh
$3,915
-
kW-mo/yr
$1,260
-
lb
TOTAL IMPLEMENTED $4,333 $10,864 $3,073
56,272
kWh
- $1,260
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs