ITAC Assessment: CO0409
ITAC logo
ITAC Assessment: CO0409
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product blank videotapes
NAICS
n/a
SIC 3695: Magnetic And Optical Recording Media
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 33,000
ft2
Annual Production 6,500,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $15,269 827,667
kWh
Electricity Demand $22,363 1,543
kW-mo/yr
Electricity Fees $216 -
Natural Gas $4,054 941
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $584,860 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Product Savings
01 2.7224: Reduce space conditioning during non-working hours $640 $600 n/a - - $640
-
MMBtu
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $440 $628 n/a $191
9,965
kWh
$249
-
kW-mo/yr
- - - - -
03 2.4221: Install compressor air intakes in coolest locations $380 $400 n/a $170
9,086
kWh
$210
-
kW-mo/yr
- - - - -
04 2.7447: Install vinyl strip / high speed / air curtain doors $250 $190 n/a $10
586
kWh
- $240
-
MMBtu
- - - -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,690 $2,500 n/a - - - $1,690
-
lb
- - -
06 3.6192: Use a less expensive method of waste removal $260 - n/a - - - $(-50.0)
-
lb
$310
-
lb
- -
07 4.631: Install an uninteruptable power supply $234,000 $4,800 n/a - - - - - - $234,000
08 4.521: Clear and rent existing space $208,000 $(-173,400.0) n/a - - - - - $208,000 -
09 4.711: Initiate a total quality management program $139,200 $9,200 n/a - - - - - $31,200 $108,000
TOTAL RECOMMENDED $584,860 $(-155,082.0) $371
19,637
kWh
$459
-
kW-mo/yr
$880
-
MMBtu
$1,640
-
lb
$310
-
lb
$239,200 $342,000
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs