Assessment Year | 1997 |
---|---|
Principal Product | injection molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
96,600
ft2
|
Annual Production | 621
ton
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,347 | 3,385,111 |
kWh
|
$0.022 |
Electricity Demand | $105,204 | 8,377 |
kW-mo/yr
|
$12.56 |
Electricity Fees | $144 | - |
|
- |
Natural Gas | $38,609 | 10,116 |
MMBtu
|
$3.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $134,511 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $903 | $1,277 |
$353
20,809
kWh
|
$550
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $830 | - |
$830
49,238
kWh
|
- | - | - | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $560 | $580 |
$250
14,654
kWh
|
$310
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $88 | $163 |
$38
2,345
kWh
|
$50
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $15,200 | - | - | - | - |
$2,720
-
lb
|
- | - | - | $12,480 | |
06 | 3.3125: Use distillation, evaporation to remove contaminants | $3,520 | $3,300 |
$(-10.0)
(-293)
kWh
|
- |
$3,530
-
gal
|
- | - | - | - | - | |
07 | 3.3128: Utilize other methods to remove contaminants | $900 | $1,660 | - | - |
$1,090
-
gal
|
- | - | $(-190.0) | - | - | |
08 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $240 | - | - | - | - |
$240
-
lb
|
- | - | - | - | |
09 | 4.651: Install back-up equipment | $112,270 | $50,000 |
$(-6,320.0)
(-374,560)
kWh
|
$(-14,320.0)
-
kW-mo/yr
|
- | - | $(-101,090.0) | - | $234,000 | - | |
TOTAL RECOMMENDED | $134,511 | $56,980 |
$(-4,859.0)
(-287,807)
kWh
|
$(-13,410.0)
-
kW-mo/yr
|
$4,620
-
gal
|
$2,960
-
lb
|
$(-101,090.0) | $(-190.0) | $234,000 | $12,480 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs