| Assessment Year | 1997 |
|---|---|
| Principal Product | commercial printing |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
80,000
ft2
|
| Annual Production | 2,500,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,111 | 1,428,488 |
kWh
|
$0.022 |
| Electricity Demand | $63,384 | 4,752 |
kW-mo/yr
|
$13.34 |
| Electricity Fees | $153 | - |
|
- |
| Natural Gas | $5,858 | 1,583 |
MMBtu
|
$3.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,251 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,031 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,461 | $782 |
$434
24,326
kWh
|
$1,027
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $140 | $202 |
$43
2,345
kWh
|
$97
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $370 | $700 |
$130
7,327
kWh
|
$240
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $310 | $730 |
$90
5,275
kWh
|
$220
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 3.8142: Distill contaminated solvents for reuse | $3,220 | $3,600 |
$(-10.0)
(-586)
kWh
|
- | - |
$570
-
gal
|
$(-440.0) | $3,100 | - | |
| 06 | 3.5121: Recycle waste ink and cleanup solvent | $1,640 | $1,640 | - | - |
$(-4,800.0)
-
gal
|
- | - | $6,440 | - | |
| 07 | 4.653: Maintain/enlarge a stock of spare parts | $7,110 | $340 | - | - | - | - | - | - | $7,110 | |
| TOTAL RECOMMENDED | $14,251 | $7,994 |
$687
38,687
kWh
|
$1,584
-
kW-mo/yr
|
$(-4,800.0)
-
gal
|
$570
-
gal
|
$(-440.0) | $9,540 | $7,110 | ||
| TOTAL IMPLEMENTED | $11,031 | $4,394 |
$697
39,273
kWh
|
$1,584
-
kW-mo/yr
|
$(-4,800.0)
-
gal
|
- | - | $6,440 | $7,110 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs