ITAC Assessment: CO0388
ITAC logo
ITAC Assessment: CO0388
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product flow sensors
NAICS
n/a
SIC 3824: Totalizing Fluid Meters and Counting Devices
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 37,000
ft2
Annual Production 1,800
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,819 1,452,227
kWh
Electricity Demand $51,903 3,870
kW-mo/yr
Electricity Fees $154 -
Natural Gas $3,245 950
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,878 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,660

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,648 $3,958 $440
24,619
kWh
$1,208
-
kW-mo/yr
- - - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $970 $400 $320
17,878
kWh
$650
-
kW-mo/yr
- - - - - -
03 2.2437: Recover waste heat from equipment $390 $930 - - $390
-
MMBtu
- - - - -
04 2.4221: Install compressor air intakes in coolest locations $390 $330 $130
7,034
kWh
$260
-
kW-mo/yr
- - - - - -
05 2.4133: Use most efficient type of electric motors $260 $500 $40
2,345
kWh
$220
-
kW-mo/yr
- - - - - -
06 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid $3,300 $11,100 - - $40
-
MMBtu
- - - $770 $2,490
-
Tgal
07 3.6124: Burn waste oil for heat $830 $3,320 $(-10.0)
(-293)
kWh
- $80
-
MMBtu
- $760
-
gal
- - -
08 3.8132: Use less toxic and volatile solvent substitutes $1,180 $1,500 $(-50.0)
(-2,638)
kWh
$(-100.0)
-
kW-mo/yr
- - $640
-
gal
$690
-
gal
- -
09 4.425: Eliminate/reduce redundant inspections $5,910 $14,000 $(-670.0)
(-37,222)
kWh
$(-1,990.0)
-
kW-mo/yr
- $250
-
Tgal
- - $8,320 -
TOTAL RECOMMENDED $14,878 $36,038 $200
11,723
kWh
$248
-
kW-mo/yr
$510
-
MMBtu
$250
-
Tgal
$1,400
-
gal
$690
-
gal
$9,090 $2,490
-
Tgal
TOTAL IMPLEMENTED $7,660 $15,660 $(-220.0)
(-12,310)
kWh
$(-1,080.0)
-
kW-mo/yr
$390
-
MMBtu
$250
-
Tgal
- - $8,320 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs