ITAC Assessment: CO0385
ITAC logo
ITAC Assessment: CO0385
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product aerial manlifts
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $50
M
to 100
M
# of Employees 350
Plant Area 180,000
ft2
Annual Production 2,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,408 5,593,787
kWh
Electricity Demand $170,663 12,751
kW-mo/yr
Electricity Fees $157 -
Natural Gas $135,021 43,681
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $133,537 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $124,887

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4239: Eliminate or reduce compressed air usage $6,360 $6,100 $1,140
63,892
kWh
$5,220
-
kW-mo/yr
- - - - - -
02 2.1135: Repair furnaces and oven doors so that they seal efficiently $2,510 $400 - - $2,510
-
MMBtu
- - - - -
03 2.4221: Install compressor air intakes in coolest locations $1,180 $320 $490
27,257
kWh
$690
-
kW-mo/yr
- - - - - -
04 2.4133: Use most efficient type of electric motors $197 $322 $73
4,103
kWh
$124
-
kW-mo/yr
- - - - - -
05 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid $6,410 $13,700 - - - $2,260
-
gal
- $2,640 $1,510 -
06 3.4156: Use flow control valves on equipment to optimize water use $2,370 $420 - - - - - - - $2,370
-
Tgal
07 3.2121: Convert to electrostatic powder coating $105,860 $99,400 - - $(-4,880.0)
-
MMBtu
- $3,250
-
gal
$7,280 $100,210 -
08 4.621: Use fixtures to reduce machine changeout times $8,650 $10,000 - - - - $4,370
-
gal
$4,280 - -
TOTAL RECOMMENDED $133,537 $130,662 $1,703
95,252
kWh
$6,034
-
kW-mo/yr
$(-2,370.0)
-
MMBtu
$2,260
-
gal
$7,620
-
gal
$14,200 $101,720 $2,370
-
Tgal
TOTAL IMPLEMENTED $124,887 $120,662 $1,703
95,252
kWh
$6,034
-
kW-mo/yr
$(-2,370.0)
-
MMBtu
$2,260
-
gal
$3,250
-
gal
$9,920 $101,720 $2,370
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs