Assessment Year | 1997 |
---|---|
Principal Product | electrosurgical equipment |
NAICS |
n/a
|
SIC | 3845: Electromedical and Electrotherapeutic Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
67,000
ft2
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $41,158 | 1,085,873 |
kWh
|
$0.038 |
Electricity Demand | $25,832 | 3,080 |
kW-mo/yr
|
$8.39 |
Electricity Fees | $1,317 | - |
|
- |
Natural Gas | $9,473 | 2,768 |
MMBtu
|
$3.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,011 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,711 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,711 | $2,985 |
$1,004
26,377
kWh
|
$707
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $1,050 | $4,840 |
$700
18,464
kWh
|
$350
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.7224: Reduce space conditioning during non-working hours | $920 | $300 | - | - |
$920
-
MMBtu
|
- | - | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $530 | $500 |
$800
21,102
kWh
|
- |
$(-270.0)
-
MMBtu
|
- | - | - | - | - | |
05 | 3.8121: Cover containers to minimize evaporative losses | $1,680 | $10,000 | - | - | - | - | - | - | $1,680 | - | |
06 | 3.3122: Use filtration, centrifuging to remove contaminants | $620 | $760 | - | - | - |
$(-20.0)
-
gal
|
$720
-
lb
|
- | $(-80.0) | - | |
07 | 4.431: Train operators for maximum operating efficiency | $26,000 | $4,000 | - | - | - | - | - | - | - | $26,000 | |
08 | 4.112: Replace old machine with new automatic multi-station tool | $10,500 | $30,000 | - | - | - | - | - | $10,620 | $(-120.0) | - | |
TOTAL RECOMMENDED | $43,011 | $53,385 |
$2,504
65,943
kWh
|
$1,057
-
kW-mo/yr
|
$650
-
MMBtu
|
$(-20.0)
-
gal
|
$720
-
lb
|
$10,620 | $1,480 | $26,000 | ||
TOTAL IMPLEMENTED | $27,711 | $6,985 |
$1,004
26,377
kWh
|
$707
-
kW-mo/yr
|
- | - | - | - | - | $26,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs