Assessment Year | 1996 |
---|---|
Principal Product | automotive hood protectors |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
53,000
ft2
|
Annual Production | 1,092,000
pieces
|
Production Hrs. Annual | 5,408
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,212 | 2,031,653 |
kWh
|
$0.017 |
Electricity Demand | $55,393 | 4,958 |
kW-mo/yr
|
$11.17 |
Electricity Fees | $29 | - |
|
- |
Natural Gas | $8,623 | 2,222 |
MMBtu
|
$3.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $531,835 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $517,560 | $5,000 |
$(-470.0)
(-27,257)
kWh
|
$(-670.0)
-
kW-mo/yr
|
- | - | $81,900 | - | $436,800 | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,610 | $50,000 |
$5,490
317,702
kWh
|
$7,380
-
kW-mo/yr
|
$(-5,260.0)
-
MMBtu
|
- | - | - | - | |
03 | 2.6218: Turn off equipment when not in use | $2,810 | $6,710 |
$2,810
162,368
kWh
|
- | - | - | - | - | - | |
04 | 3.8142: Distill contaminated solvents for reuse | $1,865 | $3,550 |
$(-5.0)
(-293)
kWh
|
- | - |
$590
-
gal
|
$500 | $780 | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $850 | $290 |
$350
20,223
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $840 | $560 |
$(-10.0)
(-586)
kWh
|
$(-10.0)
-
kW-mo/yr
|
$860
-
MMBtu
|
- | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $300 | $280 |
$120
7,034
kWh
|
$180
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $531,835 | $66,390 |
$8,285
479,191
kWh
|
$7,380
-
kW-mo/yr
|
$(-4,400.0)
-
MMBtu
|
$590
-
gal
|
$82,400 | $780 | $436,800 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs