| Assessment Year | 1996 |
|---|---|
| Principal Product | automotive hood protectors |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 145 |
| Plant Area |
53,000
ft2
|
| Annual Production | 1,092,000
pieces
|
| Production Hrs. Annual | 5,408
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,212 | 2,031,653 |
kWh
|
$0.017 |
| Electricity Demand | $55,393 | 4,958 |
kW-mo/yr
|
$11.17 |
| Electricity Fees | $29 | - |
|
- |
| Natural Gas | $8,623 | 2,222 |
MMBtu
|
$3.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $531,835 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $517,560 | $5,000 |
$(-470.0)
(-27,257)
kWh
|
$(-670.0)
-
kW-mo/yr
|
- | - | $81,900 | - | $436,800 | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,610 | $50,000 |
$5,490
317,702
kWh
|
$7,380
-
kW-mo/yr
|
$(-5,260.0)
-
MMBtu
|
- | - | - | - | |
| 03 | 2.6218: Turn off equipment when not in use | $2,810 | $6,710 |
$2,810
162,368
kWh
|
- | - | - | - | - | - | |
| 04 | 3.8142: Distill contaminated solvents for reuse | $1,865 | $3,550 |
$(-5.0)
(-293)
kWh
|
- | - |
$590
-
gal
|
$500 | $780 | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $850 | $290 |
$350
20,223
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $840 | $560 |
$(-10.0)
(-586)
kWh
|
$(-10.0)
-
kW-mo/yr
|
$860
-
MMBtu
|
- | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $300 | $280 |
$120
7,034
kWh
|
$180
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $531,835 | $66,390 |
$8,285
479,191
kWh
|
$7,380
-
kW-mo/yr
|
$(-4,400.0)
-
MMBtu
|
$590
-
gal
|
$82,400 | $780 | $436,800 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs