ITAC Assessment: CO0376
ITAC logo
ITAC Assessment: CO0376
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product large diameter welded steel pipe
NAICS
n/a
SIC 3317: Steel Pipe and Tubes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 133,900
ft2
Annual Production 26,000
ton
Production Hrs. Annual 5,200
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,679 3,744,431
kWh
Electricity Demand $155,007 12,149
kW-mo/yr
Electricity Fees $9,057 -
Natural Gas $89,456 52,178
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,365 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,908

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,040 $1,000 - $8,040
-
kW-mo/yr
-
02 3.5313: Increase amount of waste recovered for resale $7,040 - - - $7,040
-
lb
03 2.4133: Use most efficient type of electric motors $518 $470 $115
5,569
kWh
$403
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $417 $1,818 $98
4,689
kWh
$319
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $1,380 $500 $580
27,257
kWh
$800
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,320 $350 $560
26,084
kWh
$760
-
kW-mo/yr
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $650 $2,620 $80
3,810
kWh
$570
-
kW-mo/yr
-
TOTAL RECOMMENDED $19,365 $6,758 $1,433
67,409
kWh
$10,892
-
kW-mo/yr
$7,040
-
lb
TOTAL IMPLEMENTED $10,908 $3,940 $1,335
62,720
kWh
$2,533
-
kW-mo/yr
$7,040
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs