Assessment Year | 1996 |
---|---|
Principal Product | motor vehicle instrument panels |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 215 |
Plant Area |
103,000
ft2
|
Annual Production | 180,000
pieces
|
Production Hrs. Annual | 2,184
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $56,459 | 1,772,567 |
kWh
|
$0.032 |
Electricity Demand | $46,870 | 4,663 |
kW-mo/yr
|
$10.05 |
Electricity Fees | $(-2,110.0) | - |
|
- |
Natural Gas | $12,658 | 3,486 |
MMBtu
|
$3.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,826 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,425 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,901 | $64,178 |
$7,715
241,794
kWh
|
$5,186
-
kW-mo/yr
|
- | - | |
02 | 2.7132: Install timers on light switches in little used areas | $7,840 | $7,000 |
$7,840
245,897
kWh
|
- | - | - | |
03 | 3.2172: Use automatic cleaning equipment | $3,520 | $3,600 | - | - | $2,080 | $1,440 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $660 | $2,220 |
$400
12,309
kWh
|
$260
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $570 | $220 |
$400
12,309
kWh
|
$170
-
kW-mo/yr
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $55 | $60 |
$35
1,172
kWh
|
$20
-
kW-mo/yr
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $280 | $360 |
$110
3,224
kWh
|
$170
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $25,826 | $77,638 |
$16,500
516,705
kWh
|
$5,806
-
kW-mo/yr
|
$2,080 | $1,440 | ||
TOTAL IMPLEMENTED | $4,425 | $4,240 |
$545
16,705
kWh
|
$360
-
kW-mo/yr
|
$2,080 | $1,440 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs