| Assessment Year | 1996 |
|---|---|
| Principal Product | plastic lined vessels and castings |
| NAICS |
n/a
|
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
60,700
ft2
|
| Annual Production | 350,000
lb
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,335 | 668,816 |
kWh
|
$0.035 |
| Electricity Demand | $21,878 | 3,408 |
kW-mo/yr
|
$6.42 |
| Electricity Fees | $3 | - |
|
- |
| Natural Gas | $25,040 | 4,541 |
MMBtu
|
$5.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $3,040 | $410 |
$1,640
47,186
kWh
|
$1,400
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $1,850 | $250 | - | - | - | - | $1,850 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $768 | $1,733 |
$415
12,016
kWh
|
$353
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.2437: Recover waste heat from equipment | $1,650 | $600 | - | - |
$1,650
-
MMBtu
|
- | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $74 | $220 |
$40
1,172
kWh
|
$34
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $430 | $470 |
$230
6,741
kWh
|
$200
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 3.8132: Use less toxic and volatile solvent substitutes | $(-10.0) | - | - | - | - |
$50
-
gal
|
- | $(-60.0) | |
| 08 | 3.8132: Use less toxic and volatile solvent substitutes | $(-300.0) | - | - | - | - |
$240
-
gal
|
- | $(-540.0) | |
| TOTAL RECOMMENDED | $7,502 | $3,683 |
$2,325
67,115
kWh
|
$1,987
-
kW-mo/yr
|
$1,650
-
MMBtu
|
$290
-
gal
|
$1,850 | $(-600.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs