Assessment Year | 2000 |
---|---|
Principal Product | Knitted fabric |
NAICS |
n/a
|
SIC | 2253: Knit Outerwear Mills |
Sales Range | $5 M to 10M |
# of Employees | 156 |
Plant Area |
182,640
ft2
|
Annual Production | 7,800,000
pieces
|
Production Hrs. Annual | 7,500
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $161,092 | 5,295,428 |
kWh
|
$0.030 |
Electricity Demand | $89,000 | 10,815 |
kW-mo/yr
|
$8.23 |
Electricity Fees | $7,419 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,621 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,665 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.121: Maintain clean conditions before painting | $5,811 | $13,000 | - | - |
$(-2,080.0)
-
Tgal
|
- | $7,891 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,627 | - |
$1,164
38,394
kWh
|
$1,463
-
kW-mo/yr
|
- | - | - | |
03 | 2.4323: Use optimum size and capacity equipment | $24,784 | $8,500 |
$17,219
566,530
kWh
|
$7,565
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,597 | $150 |
$1,110
35,463
kWh
|
$487
-
kW-mo/yr
|
- | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $630 | $691 |
$438
14,361
kWh
|
$192
-
kW-mo/yr
|
- | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,299 | $220 |
$902
29,601
kWh
|
$397
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,732 | $849 |
$2,421
79,719
kWh
|
$1,311
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,141 | $6,000 |
$930
30,481
kWh
|
$511
-
kW-mo/yr
|
- | $2,700 | - | |
TOTAL RECOMMENDED | $44,621 | $29,410 |
$24,184
794,549
kWh
|
$11,926
-
kW-mo/yr
|
$(-2,080.0)
-
Tgal
|
$2,700 | $7,891 | ||
TOTAL IMPLEMENTED | $10,665 | $13,841 |
$2,712
88,218
kWh
|
$2,142
-
kW-mo/yr
|
$(-2,080.0)
-
Tgal
|
- | $7,891 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs