ITAC Assessment: CO0351
ITAC logo
ITAC Assessment: CO0351
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product window coverings
NAICS
n/a
SIC 2591: Drapery Hardware and Window Blinds and Shades
Sales Range $50
M
to 100
M
# of Employees 285
Plant Area 112,000
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 6,739
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,062 4,473,329
kWh
Electricity Demand $89,773 8,931
kW-mo/yr
Electricity Fees $133 -
Natural Gas $25,654 6,279
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $219,824 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $211,537

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 3.1291: Eliminate practice of mixing waste streams $98,120 $520 $(-80.0)
(-2,638)
kWh
- - $42,000
-
Tgal
- $56,200
02 3.3131: Use evaporation to concentrate material $96,610 $7,600 $(-750.0)
(-24,619)
kWh
$(-340.0)
-
kW-mo/yr
- $97,700
-
Tgal
- -
03 2.4239: Eliminate or reduce compressed air usage $12,210 $1,450 $7,670
250,879
kWh
$4,540
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,067 $13,386 $2,889
94,373
kWh
$2,178
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,910 $190 $1,210
39,566
kWh
$700
-
kW-mo/yr
- - - -
06 2.4221: Install compressor air intakes in coolest locations $1,650 $690 $1,040
33,998
kWh
$610
-
kW-mo/yr
- - - -
07 2.2437: Recover waste heat from equipment $1,250 $1,500 - - $1,250
-
MMBtu
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,210 $40 $760
24,912
kWh
$450
-
kW-mo/yr
- - - -
09 2.4133: Use most efficient type of electric motors $167 $53 $115
3,810
kWh
$52
-
kW-mo/yr
- - - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $870 $2,270 $600
19,637
kWh
$270
-
kW-mo/yr
- - - -
11 3.8132: Use less toxic and volatile solvent substitutes $760 $1,170 - - - - $1,120
-
gal
$(-360.0)
TOTAL RECOMMENDED $219,824 $28,869 $13,454
439,918
kWh
$8,460
-
kW-mo/yr
$1,250
-
MMBtu
$139,700
-
Tgal
$1,120
-
gal
$55,840
TOTAL IMPLEMENTED $211,537 $12,773 $9,805
320,633
kWh
$5,832
-
kW-mo/yr
- $139,700
-
Tgal
- $56,200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs