ITAC Assessment: CO0347
ITAC logo
ITAC Assessment: CO0347
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Prime mover controls
NAICS
n/a
SIC 3625: Relays and Industrial Controls
Sales Range $50
M
to 100
M
# of Employees 480
Plant Area 200,000
ft2
Annual Production 150
ton
Production Hrs. Annual 4,420
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $796,826 12,084,115
kWh
Natural Gas $82,723 19,133
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,760 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,080

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $47,400 $103,210 $47,400
934,056
kWh
-
02 2.8113: Purchase gas directly from a contract gas supplier $36,010 $6,700 - $36,010
03 2.4133: Use most efficient type of electric motors $11,550 $18,840 $11,550
212,192
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $6,270 $3,330 $6,270
103,458
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,640 $5,350 $4,640
95,252
kWh
-
06 2.2612: Use cooling tower water instead of refrigeration $1,890 $2,880 $1,890
35,463
kWh
-
TOTAL RECOMMENDED $107,760 $140,310 $71,750
1,380,421
kWh
$36,010
TOTAL IMPLEMENTED $18,080 $27,070 $18,080
342,907
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs