| Assessment Year | 1993 |
|---|---|
| Principal Product | Medical Equipment |
| NAICS |
n/a
|
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | $100 M to 500M |
| # of Employees | 473 |
| Plant Area |
104,555
ft2
|
| Annual Production | 12,020
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $236,916 | 3,813,599 |
kWh
|
$0.062 |
| Natural Gas | $24,331 | 6,160 |
MMBtu
|
$3.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,320 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,200 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $5,750 | $250 | - | - | $5,750 | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,110 | $1,200 |
$2,110
33,998
kWh
|
- | - | |
| 03 | 2.2437: Recover waste heat from equipment | $2,510 | $2,100 | - |
$2,510
-
MMBtu
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $1,260 | $2,830 |
$1,260
20,223
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $500 | $840 |
$500
8,206
kWh
|
- | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $610 | $1,350 |
$610
9,965
kWh
|
- | - | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,580 | $3,915 |
$1,580
25,498
kWh
|
- | - | |
| TOTAL RECOMMENDED | $14,320 | $12,485 |
$6,060
97,890
kWh
|
$2,510
-
MMBtu
|
$5,750 | ||
| TOTAL IMPLEMENTED | $11,200 | $9,035 |
$5,450
87,925
kWh
|
- | $5,750 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs