Assessment Year | 1992 |
---|---|
Principal Product | Nickel-Cadmium Batteries |
NAICS |
n/a
|
SIC | 3691: Storage Batteries |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
53,000
ft2
|
Annual Production | 10,900
pieces
|
Production Hrs. Annual | 6,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,480 | 1,924,678 |
kWh
|
$0.076 |
Natural Gas | $38,318 | 9,876 |
MMBtu
|
$3.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,200 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,200 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $1,080 | $250 | - | - | $1,080 | |
02 | 2.2511: Insulate bare equipment | $7,370 | $830 |
$7,190
94,666
kWh
|
$180
-
MMBtu
|
- | |
03 | 2.7224: Reduce space conditioning during non-working hours | $2,380 | $1,050 |
$1,050
22,274
kWh
|
$1,330
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,910 | $780 |
$1,910
25,205
kWh
|
- | - | |
05 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $1,580 | $1,100 | - |
$1,580
-
MMBtu
|
- | |
06 | 2.4224: Upgrade controls on compressors | $600 | $150 |
$600
12,896
kWh
|
- | - | |
07 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,770 | $2,270 |
$1,770
37,515
kWh
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $190 | $690 | - |
$190
-
MMBtu
|
- | |
09 | 2.3212: Optimize plant power factor | $1,320 | $2,580 | - | - | $1,320 | |
TOTAL RECOMMENDED | $18,200 | $9,700 |
$12,520
192,556
kWh
|
$3,280
-
MMBtu
|
$2,400 | ||
TOTAL IMPLEMENTED | $18,200 | $9,700 |
$12,520
192,556
kWh
|
$3,280
-
MMBtu
|
$2,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs