Assessment Year | 1992 |
---|---|
Principal Product | Bakery Products |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
120,000
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 6,448
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $203,641 | 3,883,060 |
kWh
|
$0.052 |
Natural Gas | $142,816 | 54,929 |
MMBtu
|
$2.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,370 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,370 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $6,750 | $1,500 |
$6,750
128,664
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $710 | $250 |
$710
13,482
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,180 | $270 |
$1,180
22,567
kWh
|
- | |
04 | 2.7314: Reduce ventilation air | $3,480 | $3,580 |
$350
13,482
kWh
|
$3,130
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,160 | $(-1,240.0) |
$7,160
136,577
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,840 | $6,240 |
$1,840
24,326
kWh
|
- | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $600 | $1,000 | - |
$600
-
MMBtu
|
|
08 | 2.2136: Install / repair insulation on steam lines | $960 | $1,920 | - |
$960
-
MMBtu
|
|
09 | 2.4133: Use most efficient type of electric motors | $4,690 | $9,550 |
$4,690
90,270
kWh
|
- | |
TOTAL RECOMMENDED | $27,370 | $23,070 |
$22,680
429,368
kWh
|
$4,690
-
MMBtu
|
||
TOTAL IMPLEMENTED | $27,370 | $23,070 |
$22,680
429,368
kWh
|
$4,690
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs