ITAC Assessment: CO0232
ITAC logo
ITAC Assessment: CO0232
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product Asphalt and Concrete
NAICS
n/a
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $1
M
to 5
M
# of Employees 29
Plant Area 4,160
ft2
Annual Production 220,000
ton
Production Hrs. Annual 3,337
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,693 774,912
kWh
Natural Gas $206,007 74,103
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,490 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,220

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.8121: Apply for tax-free status for energy purchases $2,400 $250 $2,400
-
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $4,760 $1,500 - $4,760
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $1,210 $670 - $1,210
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $360 $150 $360
5,275
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $6,640 $3,600 - $6,640
-
MMBtu
06 2.4224: Upgrade controls on compressors $780 $500 $780
11,723
kWh
-
07 2.2511: Insulate bare equipment $850 $1,700 - $850
-
MMBtu
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,740 $6,570 $2,740
33,705
kWh
-
09 2.6212: Turn off equipment during breaks, reduce operating time $2,440 $2,440 $2,440
36,635
kWh
-
10 2.4133: Use most efficient type of electric motors $2,040 $6,300 $2,040
25,791
kWh
-
11 2.4133: Use most efficient type of electric motors $270 $670 $270
2,638
kWh
-
TOTAL RECOMMENDED $24,490 $24,350 $11,030
115,767
kWh
$13,460
-
MMBtu
TOTAL IMPLEMENTED $24,220 $23,680 $10,760
113,129
kWh
$13,460
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs