ITAC Assessment: CO0197
ITAC logo
ITAC Assessment: CO0197
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product CONCRETE PIPE
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area
n/a
Annual Production 12,000
ton
Production Hrs. Annual 2,820
hrs
Location (State) Wyoming

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,658 308,030
kWh
Natural Gas $34,230 7,307
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,667 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,508

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.8121: Apply for tax-free status for energy purchases $1,847 $250 $597
-
kWh
$1,250
-
MMBtu
02 2.4133: Use most efficient type of electric motors $161 $383 $161
3,224
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $725 $516 $725
14,068
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $500 $200 $500
9,672
kWh
-
05 2.7261: Install timers and/or thermostats $434 $450 - $434
-
MMBtu
TOTAL RECOMMENDED $3,667 $1,799 $1,983
26,964
kWh
$1,684
-
MMBtu
TOTAL IMPLEMENTED $2,508 $833 $1,258
12,896
kWh
$1,250
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs