ITAC Assessment: CO0172
ITAC logo
ITAC Assessment: CO0172
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product INJECTION MOLDED PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area
n/a
Annual Production 100,000
pieces
Production Hrs. Annual 6,480
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,379 663,247
kWh
Natural Gas $2,812 662
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,068 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,068

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $758 $524 $758
14,654
kWh
-
02 2.8121: Apply for tax-free status for energy purchases $1,070 $250 $1,004
-
kWh
$66
-
MMBtu
03 2.6223: Schedule use of elevators to conserve energy $420 $300 $420
8,206
kWh
-
04 2.2443: Re-use or recycle hot or cold process exhaust air $340 $600 - $340
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $300 $880 $300
5,862
kWh
-
06 2.6232: Install set-back timers $180 $100 $180
3,517
kWh
-
TOTAL RECOMMENDED $3,068 $2,654 $2,662
32,239
kWh
$406
-
MMBtu
TOTAL IMPLEMENTED $3,068 $2,654 $2,662
32,239
kWh
$406
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs