ITAC Assessment: CO0171
ITAC logo
ITAC Assessment: CO0171
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product POLYURETHANE COATINGS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 15
Plant Area
n/a
Annual Production 260,000
lb
Production Hrs. Annual 2,210
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,561 584,994
kWh
Natural Gas $25,244 5,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,117 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,795

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.8121: Apply for tax-free status for energy purchases $2,837 $200 $1,543
-
kWh
$1,294
-
MMBtu
02 2.4131: Size electric motors for peak operating efficiency $300 $200 $300
5,862
kWh
-
03 2.7261: Install timers and/or thermostats $1,290 $50 $540
10,258
kWh
$750
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $288 $339 $288
5,862
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $80 $177 $80
1,465
kWh
-
06 2.7243: Improve air circulation with destratification fans / other methods $1,322 $3,600 $(-38.0)
(-586)
kWh
$1,360
-
MMBtu
TOTAL RECOMMENDED $6,117 $4,566 $2,713
22,861
kWh
$3,404
-
MMBtu
TOTAL IMPLEMENTED $4,795 $966 $2,751
23,447
kWh
$2,044
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs